Key takeaways
- In a W12x26 the 26 is pounds per foot
- Light, complex steel costs more per ton than heavy repetitive steel
- Price joists, deck and miscellaneous metals separately
- Compare pounds of steel per square foot with similar structures
Structural steel is usually priced by the ton. It is a convenient way to compare bids and budgets, but a ton of steel on one project can cost very differently from a ton on another. This guide explains what goes into steel cost per ton and how to estimate tonnage accurately.
What "cost per ton" can include
A steel price may include some or all of these parts:
- Mill material: beams, columns, angles, plates and tubes
- Detailing: shop drawings and connection design if delegated
- Fabrication: cutting, drilling, welding and assembling in the shop
- Connections: plates, bolts and welds
- Surface preparation and coatings: shop primer, galvanizing or fireproofing-ready finishes
- Delivery to site
- Erection: crane, ironworkers, bolting, field welding and plumbing the frame
- Metal deck and joists, sometimes priced separately
When comparing quotes, line them up by these parts. One supplier's "furnish only" price is not comparable to another's "furnish and erect".
Why cost per ton varies
| Factor | Effect on cost per ton |
|---|---|
| Member weight | Light members have more connections and handling per ton, so cost more per ton |
| Connection complexity | Moment connections and many unique details add fabrication hours |
| Repetition | Repeating bays and members fabricate and erect faster |
| Coatings | Galvanizing and special paint systems add cost |
| Site access | Tight sites need smaller cranes and more lifts |
| Building height | Taller structures need more crane time and safety measures |
| Market prices | Mill prices and tariffs change over time |
| Schedule | Fast schedules may need overtime or multiple crews |
How to estimate structural steel tonnage
Step 1: Gather the drawings
Use the framing plans for each level, the column schedule, elevations, bracing details, connection details and the structural general notes.
Step 2: List every member
For each beam, girder, column and brace, record the section size (for example W12x26) and the length. Remember that the number after the "x" in a wide-flange designation is its weight in pounds per foot.
Step 3: Calculate weight
Weight = length × weight per foot. A 30-foot W12x26 beam weighs about 780 pounds.
Step 4: Add connections
Connection material such as plates, angles and bolts is often added as a percentage of the main member weight, or calculated from the connection details for accuracy.
Step 5: Add miscellaneous steel
Lintels, embed plates, roof frames for mechanical units, stair stringers, railings and ladders are often in Division 05 as miscellaneous metals. Price them separately, because they are labor-heavy for their weight.
Step 6: Joists and deck
Steel joists are priced by the joist supplier, and metal deck by the square foot. Keep them on separate lines.
Step 7: Price each part
Apply prices for material, fabrication, coatings, delivery and erection per ton, adjusted for the project's complexity.
Example
A small building with 120 tons of structural steel, 30 tons of joists and 45,000 SF of roof deck would be estimated as three separate lines, each with its own unit pricing, plus miscellaneous metals such as lintels and roof frames.
Common mistakes
- Comparing furnish-only and furnish-and-erect prices
- Missing connection weight
- Forgetting miscellaneous metals
- Leaving out crane mobilization and erection equipment
- Ignoring fireproofing or galvanizing requirements in the specs
- Not checking for delegated connection design
Check your total
Compare pounds of steel per square foot of building with similar structures. A low number may mean missed members or levels; a high number may mean heavy transfer structures or long spans.
Erection costs and crane planning
Erection can be a large part of steel cost, and it depends on how the frame goes up. The size and number of cranes, the number of picks per day, the distance from the crane to each piece and the site layout all affect production. Tight urban sites may need smaller cranes and more moves, while open sites allow larger cranes and faster erection. Include crane mobilization, rigging, safety equipment, bolting and field welding, plus surveying to plumb the frame. Ask erectors for quotes based on your tonnage and piece count, because piece count often drives erection time more than weight.