Estimating guide · Aug 11, 2026 · 5 min read

General conditions in construction: what's included and what percentage to expect

What are general conditions in construction? What's included, typical percentage ranges, how to price them by duration and the items most often missed.

General conditions in construction: what's included and what percentage to expect – Premium Estimating LLC guide
Quick answer: General conditions are the job-site costs of running a project that are not part of any single trade, such as supervision, the site trailer, temporary utilities, toilets, fencing, dumpsters and cleanup. On many commercial projects they fall around 5% to 15% of construction cost, but they depend mainly on project duration.

Key takeaways

  • General conditions are job costs; overhead is company cost
  • Price them line by line against the schedule
  • Small, long or occupied-building projects carry higher percentages
  • Check Division 01 for owner requirements that add cost

General conditions are the costs of running a construction project that are not part of any single trade. They keep the job going: the people who manage it, the temporary facilities on site and the services that every trade relies on. On commercial work they are a large and often underestimated part of the bid.

General conditions vs general requirements vs overhead

These terms are often mixed up:

  • General conditions usually means the job-site costs of the contractor for this project.
  • General requirements is CSI Division 01, the section of the specifications that tells you what the owner requires, such as temporary facilities, testing, submittals and closeout. Many of those requirements become general conditions costs.
  • Overhead is the cost of running your company, such as the main office, accounting, estimating and insurance not tied to one job.

Keeping these separate in your estimate makes it easier to compare jobs and to defend your numbers.

What is included in general conditions

A typical list for a commercial project:

Personnel - Superintendent for the full duration - Project manager and project engineer time - Safety manager or safety visits - Field labor for general cleanup and small tasks

Temporary facilities - Site office trailer, furniture and storage containers - Temporary toilets and hand wash stations - Temporary fencing, gates and signage - Temporary power, water and lighting

Services - Dumpsters and trash hauling - Progress cleaning and final cleaning - Surveying and layout - Testing and inspections not paid by the owner - Permits and fees, if in your scope

Equipment and tools - Small tools and consumables - Hoisting, lifts or a forklift shared by trades - Job vehicles

Insurance and administration - Builder's risk, if required by the contract - Job-specific insurance and bonds, if not carried separately - Printing, phones, internet and software for the site

Typical percentage ranges

Contractors often ask what percentage of the job general conditions should be. There is no single answer, because the cost depends mainly on duration, not on the value of the work. A 12-month project needs 12 months of superintendent, trailer and toilets whether it costs $2 million or $5 million.

As a rough guide, many commercial projects end up somewhere between about 5% and 15% of construction cost. Smaller jobs, renovations in occupied buildings and projects with long schedules sit at the higher end. Large, fast projects often sit lower. Use these numbers only as a reasonableness check.

How to price general conditions properly

The most accurate method is to price them line by line against the schedule:

  1. Start with the schedule. How many weeks or months is the project?
  2. List time-based costs. Superintendent, trailer, toilets, fencing rental and temporary utilities are priced per week or month multiplied by duration.
  3. List one-time costs. Mobilization, trailer setup, permits and final cleaning.
  4. List quantity-based costs. Dumpster pulls estimated from the size of the project and the amount of demolition.
  5. Check Division 01. The specs may require items you would not normally carry, such as a dedicated owner's field office, extra photo documentation or specific testing.

Pricing this way means that if the schedule changes, you can adjust general conditions accurately, which is also useful when negotiating time extensions.

Items most often missed

  • Winter protection and temporary heat
  • After-hours or weekend supervision in occupied buildings
  • Closeout documents, O&M manuals and as-built drawings
  • Final cleaning, including window cleaning
  • Street use permits, traffic control and flaggers
  • Dust and noise control required by the specs
  • Small tools and consumables on long projects

General conditions on a subcontractor bid

Subcontractors have general conditions too, even if they are smaller: a foreman's non-productive time, mobilization, small tools, their own trailer or storage, and cleanup of their work. Leaving them out makes a trade bid look cheaper but cuts directly into margin.

General conditions on renovation projects

Renovations and work in occupied buildings usually have much higher general conditions than new construction of the same value. Work may have to happen at night or in phases, which stretches supervision over a longer time. Temporary partitions, dust control, protection of finished areas and extra cleaning are needed every day. Moving furniture, keeping exits open and coordinating with building staff also take time. When you estimate a renovation, start from the phasing plan and price general conditions for each phase, rather than applying the percentage you would use on a new building.

Checking your number

Once you have priced general conditions, compare them with past jobs of similar duration rather than similar value. If your total looks far above or below your history, look for a missing item or a duplicate.

Our general contractor estimates include general conditions priced for the project's duration, shown as separate lines you can adjust. See the format in our GC sample estimate.

Need numbers you can bid from? Send us your plans for a quote, see our pricing or download our sample estimates.
FAQ

Common questions

Can't find your answer? Call (850) 343-4090 or email info@premiumestimatings.com.

What is the typical percentage for general conditions?

It varies widely with project size and duration. On many commercial projects general conditions fall somewhere around 5% to 15% of construction cost, but pricing them line by line for the real schedule is more accurate than using a percentage.

Are general conditions the same as overhead?

No. General conditions are job-site costs for one project. Overhead is the cost of running your company, such as the office and accounting, spread over all projects.

Is the superintendent part of general conditions?

Yes. Project supervision, including the superintendent and usually the project manager's time on the job, is one of the largest general conditions items.

Free download: The Commercial Bid Estimating Guide 2026, a printable checklist of commonly missed scope by CSI division. Get the PDF →
Send plans

Send Us the Plans. Get a Quote.

Send your drawings and we'll reply with a price and delivery date before any work starts.

  • Clear price and delivery date up front
  • NDA signed on every project
  • Excel estimate organized by CSI division
  • Marked-up plans showing every quantity
  • 50% to start, 50% on delivery
Prefer email or phone?info@premiumestimatings.com(850) 343-4090

Your details

Upload drawings / plans
Drop files here or click to browsePDF, ZIP, DWG, DXF, XLSX, DOC, JPG · up to 5 files, 8 MB total
    Large plan sets: share a link instead of uploading.

    By sending, you agree to our Privacy Policy.

    Get a Quote Chat on WhatsApp