Key takeaways
- The pressure class and spec set the sheet metal gauge
- Fittings take much more labor than straight duct
- Fire and smoke dampers are expensive and easy to miss
- Compare pounds of duct per square foot with similar buildings
Ductwork is often the largest part of an HVAC installation in commercial buildings, and one of the hardest to estimate accurately. A good ductwork estimate measures every run and fitting, converts it to pounds of sheet metal, adds accessories and insulation, and applies realistic fabrication and installation labor. Here is how experienced mechanical estimators approach it.
Step 1: Review the mechanical drawings and specs
Start with:
- Duct layout plans for each floor
- Sections and details for risers and shafts
- Equipment schedules for air handlers, rooftop units and fans
- Diffuser, register and grille schedules
- Specifications for duct construction class, pressure class, gauge tables, sealing class, insulation and lining
The pressure class and specified standard determine the required sheet metal gauge, reinforcement and sealing, which all affect cost.
Step 2: Measure rectangular duct
For each run, record width, height and length. Group runs by size. To estimate weight:
- Find the perimeter: 2 × (width + height), in feet.
- Multiply by the length to get square feet of sheet metal.
- Choose the gauge from the specification table based on the largest dimension and pressure class.
- Multiply square feet by the weight per square foot of that gauge.
- Add an allowance for seams, joints and reinforcement.
For example, a 24 × 12 inch duct has a perimeter of 6 feet. Fifty feet of it uses about 300 square feet of sheet metal before allowances, which is then converted to pounds using the gauge weight.
Step 3: Measure round and spiral duct
Round and spiral duct is usually priced per linear foot by diameter, from supplier pricing, rather than fabricated by the pound. Count fittings separately: elbows, tees, reducers and taps.
Step 4: Count fittings
Fittings take far more labor and material than straight duct. Count elbows, transitions, offsets, tees, end caps and takeoffs. Many estimators convert each fitting to an equivalent length of straight duct or price fittings separately.
Step 5: Add accessories
- Volume dampers
- Fire dampers and fire/smoke dampers, often with electrical connections
- Access doors
- Turning vanes
- Flexible duct and connections
- Diffusers, registers and grilles
- Louvers and roof curbs if in scope
Fire and smoke dampers are expensive and easy to miss, so check every rated wall and floor penetration.
Step 6: Insulation and lining
Check the specs for which ducts need exterior wrap, internal lining or both. Measure the area of each. Duct insulation is sometimes subcontracted, but it must be included somewhere.
Step 7: Hangers and supports
Hangers, rods, anchors and supports are needed at regular spacing. Some estimators include them as a percentage of duct weight, others count them. Seismic bracing may be required in some regions.
Step 8: Labor
Labor is usually split into:
- Shop fabrication: labor per pound for rectangular duct and fittings
- Field installation: labor per pound or per foot, adjusted for height, access and building type
- Accessories: labor per item
Adjust for working conditions: high ceilings, tight plenum spaces, occupied buildings and phased work all reduce productivity.
Step 9: Equipment and the rest of the HVAC scope
Ductwork is only part of the mechanical estimate. Air handlers, rooftop units, VAV boxes, fans, piping, controls, test and balance, and startup all need to be priced too. See our full HVAC estimating service.
Common mistakes
- Using the wrong gauge for the pressure class
- Leaving out fittings or underestimating their labor
- Missing fire dampers at rated walls
- Forgetting insulation on supply ducts
- Measuring plans without checking sections where duct rises
- Not including duct cleaning or sealing tests required by spec
Check your estimate
Compare total pounds of duct per square foot of building with similar projects. A big difference usually means a missing floor, a scale problem or a different design approach.
Fabricated vs purchased duct
Many mechanical contractors fabricate rectangular duct in their own shop and buy round and spiral duct from suppliers. Some buy all duct pre-fabricated. The pricing method should match how you will actually buy it: shop labor per pound for in-house fabrication, or supplier prices per foot and per fitting for purchased duct. On large projects, ask fabricators for quotes based on your takeoff, and compare with your own shop cost. Remember to include delivery, storage on site and the handling labor needed to move duct to each floor.
Need an HVAC takeoff?
Premium Estimating LLC prepares mechanical estimates with ductwork measured by size and converted to pounds, fittings and accessories counted, insulation measured and labor hours on every line. Our HVAC sample from a government boarding school shows more than 400 line items. Download it from the sample estimates page.