Key takeaways
- Count doors and frames as separate items
- Pairs of doors need extra hardware such as flush bolts
- Fire-rated openings need labeled doors, frames and hardware
- Clarify who furnishes and installs electrified hardware
Doors, frames and hardware look like a simple count, but they are one of the most detail-heavy parts of an estimate. A single project can have dozens of door types, several frame types, fire ratings and many hardware sets. Reading the door schedule and hardware specification carefully is the key to an accurate Division 08 estimate.
Where the information is
- Door schedule: usually on an architectural sheet, listing every door
- Door and frame elevations: show door types (flush, half-glass, full-glass) and frame profiles
- Frame details: jambs, heads and sills for different wall types
- Hardware specification (Section 08 71 00): defines each hardware set
- Floor plans: show door locations and swing
Reading the door schedule
Typical columns:
| Column | What it tells you |
|---|---|
| Door number | Matches the plan tag |
| Size | Width × height × thickness |
| Door type | Elevation reference, such as flush or with vision lite |
| Door material | Hollow metal, wood, aluminum, FRP |
| Frame type and material | Hollow metal, aluminum, wood; welded or knock-down |
| Fire rating | 20, 45, 60 or 90 minutes, or none |
| Hardware set | Group number from the hardware spec |
| Glazing | Type of glass in vision lites |
| Remarks | Special notes: acoustic, lead-lined, electrified |
Count doors by unique combinations of size, type, material and rating. Each combination may have a different price.
Frames
Count frames separately from doors. Note frame type (single or pair), depth to match the wall thickness, anchors for the wall type, and fire label. Borrowed lites and sidelights may be part of frames.
Hardware sets
The hardware specification lists each set with its items and quantities, for example:
- Hinges (3 per leaf, or continuous hinge)
- Lockset or latchset with function
- Exit device on egress doors
- Closer
- Kick plate and stops
- Weatherstripping and threshold on exterior doors
- Silencers or seals
Multiply each set by the number of doors assigned to it. Hardware for pairs of doors includes extra items such as flush bolts and coordinators.
Electrified hardware and access control
Doors with card readers, electric strikes, electrified locks, automatic operators or door position switches need:
- Electrified hardware items
- Power transfer hinges or wire loops
- Power supplies
- Coordination with the electrical and security contractors
Identify who furnishes and who installs each part. These items are frequently missed or double-counted between trades.
Fire-rated openings
Fire-rated doors and frames must be labeled assemblies, with rated hardware and closers. Glass in rated doors must be rated glazing. Rated openings cost more and may need inspection.
Installation labor
Price labor separately for:
- Setting frames (often during wall framing)
- Hanging doors
- Installing hardware by set complexity
- Adjusting and final hardware
Common takeoff errors
- Counting doors but not frames
- Missing pairs of doors (counting as one)
- Ignoring fire ratings
- Not multiplying hardware sets correctly
- Missing electrified hardware coordination
- Forgetting doors shown only in enlarged plans or on other floors
- Leaving out access panels and overhead doors if in scope
Hardware submittals and allowances
On some projects the hardware specification is not complete at bid time, and the documents include a hardware allowance instead. In that case, carry the allowance exactly as stated and price installation separately, unless the allowance says it includes installation. When the hardware schedule is complete, the hardware supplier usually prepares a detailed submittal after award, listing every item by door. Compare the submittal with your estimate early to catch differences.
Specialty doors
Overhead coiling doors, sectional doors, fire shutters, sliding glass doors, automatic entrances, revolving doors and access panels are also Division 08 items, often bought from specialty suppliers. Count them from the plans and schedules and get quotes including installation, operators, controls and electrical connections where needed.