How to estimate prevailing wage and Davis-Bacon projects

How to estimate prevailing wage and Davis-Bacon projects: wage determinations, fringe benefits, classifications, certified payroll and pricing tips.

How to estimate prevailing wage and Davis-Bacon projects – Premium Estimating LLC guide
Quick answer: To estimate a prevailing wage project, use the wage determination in the bid documents for the correct county and construction type, build a loaded hourly rate for each classification including fringe benefits, payroll taxes and insurance, match classifications to the actual work, and add time for certified payroll and compliance.

Key takeaways

  • Use the exact wage determination for the county and construction type
  • Add taxes and insurance on top of wage plus fringe
  • Assign the correct classification to each task
  • Confirm subcontractors priced prevailing wages too

Prevailing wage projects pay higher labor rates and come with extra paperwork. Contractors who price them using their normal crew rates often lose money, while those who understand the rules can win steady public work. This guide explains how to estimate prevailing wage and Davis-Bacon jobs correctly.

What prevailing wage means

On many public projects, the law requires contractors to pay at least a set hourly wage plus fringe benefits to each worker, based on the trade and the county where the work is done. These rates are published in a wage determination that is included in the bid documents.

At the federal level, the Davis-Bacon Act applies to federally funded or assisted construction contracts above a set value. Many states have their own prevailing wage laws for state and local public work, sometimes with different rates and rules.

Step 1: Find the right wage determination

The bid documents should include or reference the wage determination. Check:

  • The determination number and modification date
  • The county and type of construction (building, heavy, highway or residential)
  • Every classification you will use, such as electrician, laborer, carpenter or operator

Using rates from the wrong county or construction type is one of the most common pricing errors.

Step 2: Build a loaded labor rate per classification

For each classification, calculate the true hourly cost:

  1. Base wage from the determination
  2. Fringe benefits from the determination, paid as benefits or cash
  3. Payroll taxes: Social Security, Medicare, unemployment
  4. Workers' compensation at your rate for that trade
  5. General liability if it is based on payroll
  6. Overtime premiums if the schedule needs them

Note that workers' compensation and some taxes are based on wages, so a higher base wage also raises those costs.

Step 3: Match classifications to the work

Prevailing wage rules require each worker to be paid for the work they actually perform. A laborer cannot install electrical conduit at the laborer rate. When you build crews in your estimate, assign the right classification to each task and check whether apprentices are allowed and at what ratio.

Step 4: Adjust productivity

The wage rate is fixed, so productivity becomes the main lever. Consider:

  • Site restrictions on public facilities, such as schools in session
  • Security clearances or escort requirements on government sites
  • Working hours limited by the owner
  • Additional safety requirements

Step 5: Add administrative costs

Prevailing wage jobs need:

  • Certified payroll reports, usually weekly
  • Posting of wage notices on site
  • Tracking of apprentice ratios
  • Subcontractor payroll compliance
  • Possible audits

These take office time. Add an allowance in general conditions or overhead for compliance.

Step 6: Check your subcontractors

Make sure your subcontractors priced prevailing wages too. A low sub quote based on open-shop rates will either be withdrawn or create compliance problems later. Ask subs to confirm in writing that their price includes prevailing wages and certified payroll.

Pricing example

Suppose an electrician classification has a base wage of $45.00 and fringe of $20.00 per hour in the wage determination. Add payroll taxes and workers' compensation, which might add roughly another $8.00 to $12.00 per hour depending on your rates. The loaded cost is then around $73 to $77 per hour before overhead and profit, much higher than a typical non-prevailing open-shop rate. Multiply that by the labor hours in your estimate, and the difference on a large job is significant.

The numbers above are only an illustration. Always use the actual determination for your project.

Common mistakes

  • Using the wrong county or construction type
  • Leaving out fringe benefits
  • Not loading taxes and insurance on top of the wage
  • Assigning lower classifications to skilled work
  • Forgetting certified payroll and compliance time
  • Accepting sub quotes that did not include prevailing wages

State and local differences

Each state that has a prevailing wage law publishes its own rates, rules and forms. Some states set rates by county and craft much like the federal system, while others base them on collective bargaining agreements. Thresholds, apprentice ratios, overtime rules and reporting forms also differ. When you bid in a new state, read that state's labor department guidance before pricing, and check whether both federal and state rules apply to the same project. On jobs with both, the higher rate for each classification usually applies.

Getting help with public bids

Public bids have strict forms, alternates, unit prices and wage rules. Premium Estimating LLC prices labor against the project's wage determination and follows the bid form layout. Learn more about our public and government bid estimating, or see a government project in our HVAC sample estimate.

Need numbers you can bid from? Send us your plans for a quote, see our pricing or download our sample estimates.
FAQ

Common questions

Can't find your answer? Call (850) 343-4090 or email info@premiumestimatings.com.

What is a prevailing wage?

The minimum hourly wage and fringe benefits that must be paid to each worker classification on certain public projects, set for the specific county and trade.

What is Davis-Bacon?

A federal law that requires prevailing wages on federally funded or assisted construction contracts above a set value. Many states have similar laws for state and local projects.

Do prevailing wage rates change during a project?

The rates that apply are usually fixed by the wage determination in the contract, but some multi-year contracts or modifications can bring updated rates, so check the contract terms.

Free download: The Commercial Bid Estimating Guide 2026, a printable checklist of commonly missed scope by CSI division. Get the PDF →
Send plans

Send Us the Plans. Get a Quote.

Send your drawings and we'll reply with a price and delivery date before any work starts.

  • Clear price and delivery date up front
  • NDA signed on every project
  • Excel estimate organized by CSI division
  • Marked-up plans showing every quantity
  • 50% to start, 50% on delivery
Prefer email or phone?info@premiumestimatings.com(850) 343-4090

Your details

Upload drawings / plans
Drop files here or click to browsePDF, ZIP, DWG, DXF, XLSX, DOC, JPG · up to 5 files, 8 MB total
    Large plan sets: share a link instead of uploading.

    By sending, you agree to our Privacy Policy.

    Get a Quote Chat on WhatsApp