Key takeaways
- Start with the documents and addenda you priced
- Specific exclusions beat copied generic lists
- Do not exclude work the specs clearly require
- Attach your scope letter to the contract
A bid is more than a number. The scope letter that comes with it, listing inclusions, exclusions and clarifications, defines what that number buys. Clear scope letters protect contractors from disputes and help owners and GCs compare bids fairly. Vague or copied ones cause arguments after award. This guide shows how to write them well.
Three parts of a scope letter
- Inclusions: what your price covers
- Exclusions: what your price does not cover
- Clarifications: the assumptions and interpretations behind your price
Start with the basis of the bid
List exactly what you priced from:
- Drawing set name and date
- Specification sections
- Addenda by number and date
- Site visit or pre-bid meeting notes
This protects you if later revisions change the scope.
Write inclusions clearly
Organize inclusions by specification section or area, in plain language. For example:
- "Furnish and install all interior metal stud framing and gypsum board per wall types on A-501, including walls to deck where indicated."
- "All plumbing fixtures per schedule on P-001, including carriers."
Clear inclusions make it easy for a reviewer to confirm your scope.
Write specific exclusions
Good exclusions are specific to the project:
- "Excludes rock excavation; unit price provided"
- "Excludes temporary power; by GC"
- "Excludes patching and painting of walls after electrical rough-in"
- "Excludes permit fees; permit application included"
Avoid long generic lists copied from old bids, especially items that contradict the specifications. Excluding work that the specs clearly require for your trade may make your bid non-compliant.
Typical clarifications
- Working hours assumed: normal weekday hours
- Number of mobilizations
- Schedule or duration assumed
- Material pricing validity date
- Testing and inspections by others
- Who provides hoisting, dumpsters or storage
- Payment terms and retainage
- Escalation terms for volatile materials (see our escalation guide)
Examples by trade
Electrical: low voltage by others, utility company fees by owner, fire alarm included per spec section 28 31 00.
Plumbing: site utilities beyond 5 feet from the building by others, gas meter by utility, fixtures per schedule.
Concrete: testing by owner, winter protection included for slabs only, vapor barrier included.
Drywall: Level 4 finish except where noted Level 5, fire caulking at rated walls included.
Alternates and unit prices
List each alternate price and unit price separately, and clarify what each includes.
Keep it readable
- Use short bullet points
- Use the same section numbers as the specs
- Keep it to one or two pages where possible
- Avoid legal language that hides meaning
Get it into the contract
After award, make sure your scope letter is attached to the subcontract or referenced in the contract. If the GC's subcontract scope differs, resolve it before signing.
Common mistakes
- No list of documents used
- Copy-pasted exclusions from another job
- Excluding work required by the specs
- No clarification of assumed schedule or hours
- Not attaching the scope letter to the contract
How owners and GCs read your scope letter
Owners and general contractors compare scope letters side by side when choosing a bidder. They look for items that are excluded or assumed differently from other bids, and they add the cost of those items back. A short, clear letter that follows the specification sections is easy to compare and often makes your price look more complete. A long list of vague exclusions makes them assume the worst. Before sending your bid, read your scope letter as if you were the person evaluating it, and remove anything that is not relevant to this project.
Updating the letter for addenda
Every addendum can change your inclusions and exclusions. When an addendum adds scope, update the letter as well as the price. When an addendum answers a question you asked, remove the related clarification or update it to match the answer.