
Key takeaways
- Read the contract's changes clause before pricing
- Include extra supervision and extended general conditions
- Request time with the cost, not later
- Keep a log of every potential and approved change
A change order is a written amendment to a construction contract that changes the scope of work, the contract price, the schedule or a combination of the three. Changes are normal on almost every project. What separates profitable contractors from struggling ones is how well they price, document and get paid for them.
What triggers a change order
- Owner changes: new rooms, upgraded finishes, added equipment
- Design errors or omissions: something missing or wrong on the drawings
- Unforeseen conditions: rock, contaminated soil, hidden structural problems in a renovation
- Code or permit requirements added after the bid
- Schedule changes: acceleration or delays caused by others
- Value engineering: reducing scope to save cost, which creates a credit change
Read the contract first
Before pricing any change, read the changes clause. It usually tells you:
- How much notice you must give and in what form
- The allowed overhead and profit on changed work
- Whether subcontractor markup is limited
- What backup the owner can require
- How time extensions are requested
Missing a notice deadline can cost you the right to be paid, even when the change is real.
How to price a change order
Price a change exactly like a small estimate, line by line.
- Define the scope. Describe exactly what is being added, deleted or changed, with reference to the RFI, sketch or bulletin.
- Take off quantities. Measure the added and deleted work from the revised drawings.
- Price material using current quotes, not the original bid prices if they have changed.
- Price labor with realistic productivity. Changed work is often less efficient than base-contract work because it is smaller, out of sequence or in a finished area.
- Add equipment and any rental time.
- Include indirect costs: extra supervision, extended general conditions, protection of finished work, cleanup.
- Add subcontractor quotes with their backup.
- Apply the allowed markups for overhead, profit and bond.
- Calculate time impact. If the change affects the critical path, request a time extension in the same change order.
For deleted work, credit the owner at a fair value, usually the cost of the deleted items with an agreed markup.
What to include on the change order form
- Change order number and date
- Reference to the RFI, bulletin or directive that caused it
- Clear description of the work
- Cost breakdown: labor, material, equipment, subcontractors, markups
- Schedule impact in days
- Signatures of owner, architect if required, and contractor
Attach the backup: takeoff, quotes and sketches. A well-documented change order gets approved faster.
Common mistakes
- Pricing from the original unit costs when material prices have moved
- Forgetting indirect costs such as supervision and extended general conditions
- Not requesting time and then being charged for delays later
- Doing the work on a verbal approval and arguing about price afterwards
- Combining many small changes without tracking each one, which makes them hard to justify
Time and material changes
Sometimes the scope of a change is not clear enough to price in advance, for example when hidden conditions are being uncovered. In that case the owner may direct the work on a time and material basis. Keep daily tickets that list every worker, their classification and hours, the materials used and the equipment on site, and get them signed by the owner's representative the same day. Unsigned tickets submitted weeks later are hard to collect. Agree in writing which labor rates and markups apply before the work starts.
Pricing credits fairly
Owners expect a fair credit when scope is deleted. Price the deleted work at current cost, not at an inflated value, and make sure the credit reflects only the work that is truly removed. If materials were already ordered or fabricated, include restocking fees or the cost of material that cannot be returned. Explaining these items clearly avoids the impression that the contractor is holding back money.
Change order logs
Keep a log of every potential change, pending change and approved change with its value and status. Review it in every owner meeting. Many contractors lose money not because changes are refused, but because small ones are never submitted.
Independent pricing of changes
Owners and agencies often need an independent check on change order pricing before approving it. Contractors sometimes need help pricing a large change quickly. Premium Estimating LLC prepares detailed change order estimates and independent cost estimates with quantities, unit costs and marked-up drawings, so the number can be reviewed line by line.