Schedule of values in construction: how to build one, with an example

How to create a schedule of values for construction pay applications: how to break down the contract, avoid front-loading, plus an example layout.

Schedule of values in construction: how to build one, with an example – Premium Estimating LLC guide
Quick answer: A schedule of values is a breakdown of the contract price into line items, each with a dollar value, used to measure progress and calculate monthly payment applications. Contractors build it from their estimate, keep it balanced instead of front-loaded, and update it with approved change orders.

Key takeaways

  • Build the SOV from your estimate so each line traces to real cost
  • Choose enough detail to measure progress without making billing a chore
  • Front-loading invites rejection and disputes
  • Use the SOV to compare billing with cost on each trade

A schedule of values (SOV) is a list that breaks the total contract price into parts, each with a dollar value. It is used every month to measure how much work is complete and how much the contractor should be paid. On most commercial projects, especially those using AIA contract forms, an approved schedule of values is required before the first payment application.

Why the schedule of values matters

  • It is the basis of every payment application.
  • It shows the owner and lender how the money is being spent.
  • It helps track progress against the budget.
  • It becomes the starting point for valuing change orders and retainage.

A clear, fair SOV speeds up payment. A vague or unbalanced one invites questions and delays.

How to build a schedule of values

1. Start from your estimate

Your bid estimate already breaks the job down by CSI division and section. Use that as the base so that each SOV line can be traced back to real costs.

2. Choose the right level of detail

Too few lines make progress hard to measure. Too many make billing a chore. A common approach on a commercial building:

  • General conditions
  • Each major trade or CSI division
  • Large trades split by area or phase, for example concrete foundations, slab on grade, elevated slabs
  • Material stored on site shown separately when the contract allows

3. Spread markups fairly

Overhead, profit and bond are usually spread across the lines in proportion to cost, or shown as separate lines if the owner requires it.

4. Check that it adds up

The total of the SOV must equal the contract sum exactly.

Example layout

Item Description Scheduled value
1 General conditions $95,000
2 Site work and utilities $140,000
3 Concrete foundations $85,000
4 Slab on grade $60,000
5 Structural steel and deck $210,000
6 Roofing $70,000
7 Doors, frames and hardware $45,000
8 Drywall and ceilings $120,000
9 Flooring and painting $75,000
10 Plumbing $90,000
11 HVAC $150,000
12 Electrical $130,000
Contract sum $1,270,000

In each payment application, the contractor shows for every line: work completed in previous periods, work completed this period, materials stored, total completed and stored, percentage complete and balance to finish. Retainage is then calculated on the completed amount.

Front-loading: why it backfires

Front-loading means putting extra value on early items, such as mobilization or foundations, to get paid sooner. It is tempting for cash flow, but it carries real risks:

  • Architects and lenders often reject an unbalanced SOV.
  • If the contractor defaults, the owner may claim it was overpaid.
  • It distorts progress reporting and damages trust.

A balanced SOV that reflects real costs gets approved faster and avoids disputes.

Retainage and the schedule of values

Most contracts hold back a percentage of each payment as retainage until the work is substantially complete. Retainage is calculated from the completed values on the schedule, so an accurate SOV also means accurate retainage. Some contracts reduce retainage once the project reaches a certain percentage complete, and some states limit retainage on public work. Track retainage on every line so that the final billing and release are simple.

Using the SOV to manage your job

The schedule of values is not only a billing tool. When each line is tied to your estimate, the project manager can compare what has been billed with what has been spent. If a line is 60% billed but 80% of its budget is already used, that trade is losing money and needs attention. Reviewing this every month catches problems while there is still time to fix them.

Tips for smoother pay applications

  • Agree the SOV before the first billing, not with it.
  • Split long-duration items into measurable parts.
  • Keep stored-materials invoices and photos ready.
  • Update the SOV with approved change orders as new lines.
  • Walk the job with the owner's representative before submitting.

From estimate to schedule of values

Because the SOV comes from the estimate, an estimate organized by CSI division with clear subtotals makes the job much easier. Every estimate from Premium Estimating LLC is delivered in Excel with division and section subtotals, so your project team can build the schedule of values directly from it. See the layout in our sample estimates.

Need numbers you can bid from? Send us your plans for a quote, see our pricing or download our sample estimates.
FAQ

Common questions

Can't find your answer? Call (850) 343-4090 or email info@premiumestimatings.com.

What is a schedule of values in construction?

A breakdown of the contract sum into line items, each with a value, used to measure progress and calculate monthly payment applications.

Who prepares the schedule of values?

The contractor prepares it and submits it to the owner or architect for approval at the start of the project.

Is the schedule of values the same as the estimate?

No. It is built from the estimate, but it is organized for billing and usually shows less detail and includes markups spread across the lines.

Free download: The Commercial Bid Estimating Guide 2026, a printable checklist of commonly missed scope by CSI division. Get the PDF →
Send plans

Send Us the Plans. Get a Quote.

Send your drawings and we'll reply with a price and delivery date before any work starts.

  • Clear price and delivery date up front
  • NDA signed on every project
  • Excel estimate organized by CSI division
  • Marked-up plans showing every quantity
  • 50% to start, 50% on delivery
Prefer email or phone?info@premiumestimatings.com(850) 343-4090

Your details

Upload drawings / plans
Drop files here or click to browsePDF, ZIP, DWG, DXF, XLSX, DOC, JPG · up to 5 files, 8 MB total
    Large plan sets: share a link instead of uploading.

    By sending, you agree to our Privacy Policy.

    Get a Quote Chat on WhatsApp