Key takeaways
- Lump sum suits buildings with complete drawings
- Unit price suits civil and utility work with uncertain quantities
- Spread mobilization and indirect costs across unit items
- Owners can reject materially unbalanced bids
Contractors bid work under different contract types, and the type changes how you estimate and where your risk sits. Two of the most common are lump sum and unit price contracts. This guide explains the difference and how to estimate each.
Lump sum contracts
In a lump sum (or stipulated sum) contract, the contractor agrees to complete the defined scope for one fixed price. If quantities turn out higher than estimated, the contractor absorbs the cost, unless the change comes from a design change or a differing site condition covered by the contract.
Common uses: buildings with complete drawings and specifications, tenant improvements, most private commercial projects.
Estimating approach:
- Take off every item carefully, because quantity errors are your risk
- Price all scope shown and specified
- Include general conditions and markups
- Clarify exclusions and assumptions in your scope letter
Unit price contracts
In a unit price contract, the owner provides estimated quantities for each item, and the contractor bids a price per unit. Payment is based on actual quantities measured in the field.
Common uses: roads, utilities, earthwork, paving, demolition, job order contracting and other work where exact quantities are not known in advance.
Estimating approach:
- Price each unit item to cover direct cost plus its share of indirect costs and markup
- Check the owner's estimated quantities against the drawings
- Consider how quantity changes affect your fixed costs
- Read how measurement and payment are defined in the specs
Comparing the two
| Feature | Lump sum | Unit price |
|---|---|---|
| Price basis | One total | Price per unit × actual quantity |
| Quantity risk | Contractor | Mostly owner |
| Design completeness needed | High | Lower |
| Payment | Progress against schedule of values | Measured quantities |
| Typical work | Buildings | Civil, utilities, roads |
Hybrid contracts
Many projects mix the two. A building contract might be lump sum with unit prices for rock excavation, unsuitable soil removal or additional piles. Public bid forms often include a base lump sum plus unit prices for items with uncertain quantities.
Spreading indirect costs
In unit price bids, there is usually no separate line for mobilization or general conditions unless the bid form has one. These costs must be spread across the unit items. If quantities drop significantly, you may not recover your fixed costs, so check whether the contract allows price adjustments for large quantity variations.
Unbalanced bids
Unbalanced bidding means pricing some items high and others low to gain an advantage, for example, if you believe certain quantities are underestimated. Owners watch for this and may reject materially unbalanced bids. It also carries risk if your assumptions are wrong. Price each item fairly.
Measuring and payment
For unit price work, documentation is essential: daily quantity records, survey data, load tickets and signed measurements. Read the measurement and payment section of the specs carefully, as it defines what each unit includes.
Job order contracting
JOC programs use a unit price book with an adjustment factor. Contractors bid a coefficient, and each task order is priced from the book. Accurate quantity takeoffs are still needed for each task. See our job order contracting estimating service.
Common mistakes
- Trusting the owner's quantities without checking
- Forgetting to spread mobilization in unit prices
- Not reading what each unit item includes
- Treating lump sum quantities loosely
Cost-plus and GMP contracts
Two other common contract types also affect estimating. In a cost-plus contract, the owner pays the contractor's actual costs plus a fee, which can be a percentage or a fixed amount. Estimates are still needed for budgeting, but the contractor carries less price risk and must keep detailed cost records. In a guaranteed maximum price (GMP) contract, the contractor is paid actual costs plus a fee up to a ceiling. The contractor carries the risk above the ceiling, so the GMP estimate must be complete, with clear allowances and contingency. Savings below the GMP are often shared.
Knowing the contract type before estimating helps you decide how detailed the estimate must be, where to show contingency, and how to document costs during the project.