Key takeaways
- Check the question deadline as soon as documents arrive
- Reference sheet, detail and spec paragraph in every RFI
- Answers come by addendum to all bidders
- Price unanswered questions with stated assumptions or alternates
Bid documents are rarely perfect. Drawings conflict with specs, details are missing and scope boundaries are unclear. Requests for information (RFIs) during bidding are how contractors get answers before they commit to a price. Used well, they reduce risk and make bids more comparable. This guide explains when and how to send pre-bid RFIs.
Why pre-bid RFIs matter
- They reduce guessing and the risk of under-pricing
- Answers are issued to all bidders by addendum, so everyone prices the same scope
- They create a record that the issue was raised
- They show the owner that you read the documents carefully
When to send them
Review the bid documents early. The instructions to bidders set a deadline for questions, often several days before bid day. Questions after the deadline may be ignored. Plan your review so questions go out well before then.
What to ask about
- Conflicts: drawings and specs disagree, or two drawings show different things
- Missing information: a detail referenced but not included, a schedule left blank
- Unclear scope: who provides an item, which trade does the work
- Quantities: for unit price items, quantities that look wrong
- Product substitutions: if allowed during bidding
- Site conditions: access, working hours, staging areas, utilities
- Schedule and phasing: unclear milestones or restrictions
How to write a good RFI
- One question per RFI where possible
- Reference the exact location: sheet number, detail, spec section and paragraph
- Describe the issue clearly, quoting the conflicting information
- Suggest a resolution when you can, which often gets a faster answer
- Keep it neutral and professional
Example:
"Sheet A-501 wall type 4 shows 3-5/8 in. studs to deck. Specification 09 22 16, paragraph 2.2.A, calls for 6 in. studs for walls over 14 ft. Walls at grid lines C–D are 18 ft high. Please confirm stud size for these walls. Suggested: 6 in. studs per specification."
Track RFIs and addenda
Keep a log of every RFI sent, the date and the answer. When addenda arrive, check that each question was answered and update your takeoff.
When no answer comes
If your question is not answered before the bid:
- Price based on the most reasonable interpretation
- State your assumption clearly in the clarifications
- Use an allowance for uncertain scope, if the bid form allows
- Consider an alternate price for the other interpretation
See our guide to bid clarifications and exclusions.
Subcontractors and RFIs
Subcontractors usually send questions through the general contractor, who forwards them to the architect. Send them early so the GC has time.
Avoid these mistakes
- Waiting until the day before the bid
- Vague questions without sheet references
- Asking questions answered in the documents
- Many questions in one long email
- Not reading addenda for answers
Using RFIs strategically
Pre-bid questions can also help a contractor stand out. A well-written RFI shows the owner and architect that your team reads documents carefully. But be careful not to reveal pricing strategies or value engineering ideas that give competitors an advantage, because answers are shared with all bidders. If you have a cost-saving idea, consider offering it as a voluntary alternate in your bid instead of asking about it in an RFI. Focus RFIs on true conflicts and missing information that affect everyone's price.
Keeping RFIs organized
Number each RFI and record the date sent, the sheet or spec reference, the question and the answer. When the addendum arrives, check off each answered question and note any that were not answered. This log becomes part of your bid file and helps if questions arise after award.
Better bid reviews
A careful document review is the first step to good RFIs. Read our guide on how to review a bid set before pricing. Premium Estimating LLC notes conflicts and missing information while preparing your takeoff, so you can send RFIs before the deadline. See our bid preparation support.