Key takeaways
- Read the geotechnical report before pricing earthwork
- Utility depth changes excavation, shoring and backfill cost
- Erosion control must be maintained for the full duration
- Rock, groundwater and unsuitable soils are the biggest risks
Sitework is often where commercial projects make or lose the most money. Earthwork volumes, soil conditions, utility depths and paving sections all carry risk. A careful sitework estimate starts with the geotechnical report and civil drawings and works through every phase of the site. This guide covers each part.
Documents you need
- Existing conditions survey and topography
- Demolition plan, if existing features are removed
- Grading and drainage plan
- Utility plans: water, sanitary sewer, storm, gas, electrical and telecom
- Paving plan and sections
- Erosion and sediment control plan
- Landscape plan
- Geotechnical report
- Specifications for Divisions 31, 32 and 33
1. Mobilization and site preparation
- Mobilization of equipment
- Construction entrance
- Clearing and grubbing by area
- Demolition of existing pavement, curbs and structures
- Tree removal and protection
2. Erosion and sediment control
- Silt fence by linear foot
- Inlet protection by count
- Sediment basins
- Stabilization and seeding
- Inspections and maintenance for the project duration
3. Earthwork
Earthwork is the most important part of the site estimate:
- Topsoil stripping and stockpiling
- Cut and fill volumes from existing and proposed grades
- Building pad preparation
- Over-excavation and replacement of unsuitable soils, as the geotechnical report requires
- Import or export of material, with haul distances
- Compaction and testing
Read our guide on how to calculate cut and fill for the methods used.
4. Site utilities
For each utility system, measure pipe length by size and material, and count structures:
- Water mains, services, valves, hydrants
- Sanitary sewer pipe, manholes and cleanouts
- Storm pipe, inlets, manholes and outfall structures
- Detention or retention systems
- Trenching, bedding, backfill and compaction
- Connections and taps to public utilities
Depth matters. Deeper trenches need more excavation, shoring or trench boxes, and more backfill.
5. Paving and hardscape
- Subgrade preparation
- Aggregate base by area and thickness
- Asphalt paving by area and lift thickness
- Concrete paving and sidewalks
- Curbs and gutters by linear foot
- Striping, signage and wheel stops
See our guide to asphalt paving cost per square foot.
6. Site improvements
- Fencing and gates
- Retaining walls
- Site furnishings, bollards and dumpster enclosures
- Site lighting bases and conduit, if in the site scope
7. Landscaping
- Topsoil placement and fine grading
- Seeding or sod
- Trees, shrubs and planting beds
- Irrigation
8. Testing and surveying
- Construction staking
- Compaction and material testing, if not by owner
- As-built surveys
Key risks to price carefully
- Unsuitable soils: the geotechnical report may recommend over-excavation
- Groundwater: dewatering can be expensive
- Rock: excavation in rock is much slower and costlier
- Haul distances: export and import costs depend on where material goes
- Utility conflicts: existing utilities not shown on the survey
Common mistakes
- Using net volumes without shrink and swell factors
- Ignoring geotechnical recommendations
- Missing trench backfill and compaction
- Forgetting erosion control maintenance for the full duration
- Leaving out utility company connection fees
Phasing and site logistics
Sitework is often done in phases. Mass grading happens first, then underground utilities, then the building pad, then curbs and paving near the end of the project. Each phase may need its own mobilization, and some areas are graded twice. Temporary stormwater controls must be adjusted as the site changes. Paving is often split into a base course early, to give trucks and trades a working surface, and a surface course at the end. Estimating each phase separately makes it easier to see the real equipment time and avoid underpricing mobilization.
Working with the geotechnical report
The geotechnical report contains information that directly changes the site estimate: depth of topsoil, groundwater levels, soil types, recommendations for over-excavation, compaction requirements, pavement sections and whether on-site soils can be reused as fill. Read the boring logs as well as the summary. If borings show rock or water near the depth of utilities or foundations, price excavation and dewatering accordingly or include clear clarifications and unit prices for these conditions.